Productivity

PROJECTS

Our Portfolio

Major Productivity Projects:

  • GIZ – Labour Standard Project: Short term assignment for production layout redesigning in partner Industrial company

    Name of assignment or project: GIZ – Labour Standard Project: Short term assignment for production layout redesigning in partner Industrial company

    Project Duration: 6 months

    Location: Sialkot

    Date of Start: May 2020

    Date of Completion:  October 2020

    Client: CONFIDENTIAL

    Main Project Features: Productivity Improvement through lean manufacturing

    Positions held: 

    Lean Consultant/Trainer 

    Role in Assignment: 

    Please refer to page # 5

    Activities performed:

    •        Establishment of IE department. 2 IEs have been hired by the company and trained under the project

    •        OJT of Line supervisors and middle management on different lean tools and techniques

    •        Set up efficient lean stitching line layout according to product flow

    •        Line balancing through ECRS

    •        Implementation on TPM tools

    •        Establishment of Lean KPIs, like

    (production /day, worker’s efficiency, productivity improvement, Reduction in Quality Defects, Lead Time, WIP, M/c breakdown and 

    reduce manufacturing cost, etc.)

    •        Implemented work station organization 

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Freelancer, Lean Implementation to improve productivity and quality of their products at M/s. Blue Horizon, Machrala Gloves Unit, Sialkot.

    Name of assignment or project: Freelancer, Lean Implementation to improve productivity and quality of their products at M/s. Blue Horizon, Machrala Gloves Unit, Sialkot.

    Project Duration: 6 months

    Location: Sialkot

    Date of Start: June 2020

    Date of Completion: November 2020

    Client: CONFIDENTIAL

    Main Project Features: Productivity Improvement through lean manufacturing system

    Positions held / Role in Assignment: 

    •   Lean Consultant/Trainer 

    •   To conduct baseline study, trainings and implementation of productivity standards improvement measures with monitoring the improvements through key performance indicators (KPIs)

    Activities performed:

    •        Establishment of IE department for sustainability of the project. 2 IEs have been hired by the company and trained under the project

    •        OJT of workers, Line supervisors and middle & top management on different lean tools and techniques

    •        Minimized product travel distance through redesigned layout of stitching production floors and Set up all stitching lines according to product flow

    •        Line balancing through ECRS

    •        Implemented Preventive Maintenance concepts through TPM tools and techniques 

    •        Establishment of Lean KPIs, like

    (production /day, worker’s efficiency, productivity improvement, Reduction in Quality Defects, Lead Time, WIP, M/c breakdown and  reduce manufacturing cost

    •        Implemented work station organization 

    •        Implemented 5S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • GIZ - Short term consultancy for the Productivity standards component in selected Industrial units (M/s. Anwar Khawaja (Pvt.) Ltd.,  - Footballs Manufacturer Unit)

    Name of assignment or project: GIZ - Short term consultancy for the Productivity standards component in selected Industrial units (M/s. Anwar Khawaja (Pvt.) Ltd.,  -

    Footballs Manufacturer Unit)

    Project Duration: 10 months

    Location: Sialkot

    Date of Start: October 2017

    Date of Completion: August 2018

    Client: CONFIDENTIAL

    Main Project Features: To implement labour standards, and to ensure the successful implementation of the dialogue approach for social compliance.  

    Positions held: 

    Lean Consultant/Trainer 

    Role in Assignment: 

    Please refer to page # 9

    Activities performed:

    •        Establishment of IE department for sustainability of the project. 4 IEs have been hired and trained under the project

    •        OJT of workers, Line supervisors and middle & top management on different lean tools and techniques

    •        Minimized product travel distance through redesigned layout of stitching production floors and Set up all stitching lines according to product flow

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at (M/s. Sheikh of Sialkot (Pvt.) Ltd., Sialkot - Leather Jackets Unit)  

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at (M/s. Sheikh of Sialkot (Pvt.) Ltd., Sialkot - Leather

    Jackets Unit)  

    Project Duration: 20 months

    Location: Sialkot

    Date of Start: Aug. 2015  

    Date of Completion: March 2017

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        Establishment of IE department for sustainability of the project. 2 IEs have been hired and trained under the project

    •        OJT of workers, Line supervisors and middle & top management on different lean tools and techniques

    •        Minimized product travel distance through re-designed layout of stitching production floors and Set up all stitching lines according to product flow

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Protech Garments Manufacturing Pvt. Ltd., Sialkot

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Protech Garments Manufacturing Pvt. Ltd.,

    Sialkot

    Project Duration: 12 months

    Location: Sialkot

    Date of Start: Feb. 2016  

    Date of Completion: Jan. 2017

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        Establishment of IE department for sustainability of the project. 1 IE has hired and trained under the project

    •        OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •        Minimized product travel distance through re-designed layout of stitching production floors and Set up all stitching lines according to product flow

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

     

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Leather Field Pvt. Ltd., Sialkot (Leather Garments Unit)

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. Leather Field Pvt. Ltd., Sialkot (Leather

    Garments Unit)

    Project Duration: 6 months

    Location: Sialkot

    Date of Start: Oct. 2016  

    Date of Completion: March 2017

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •        Minimized product travel distance through re-designed layout of stitching production floors and Set up an efficient stitching line

    according to product flow

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

     

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Servis Pvt. Ltd. Gujrat- Footwear Unit

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. Servis Pvt. Ltd. Gujrat- Footwear Unit

    Project Duration: 10 months

    Location: Gujrat

    Date of Start: Feb. 2015

    Date of Completion: Nov. 2015

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        Introduced new concept of one pair zig-zag line system

    •        Minimized product travel distance 

    •        Line balancing through ECRS

    •        OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. M. Ashraf & Sons Pvt. Limited-Karachi (Garments Unit)

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. M. Ashraf & Sons Pvt. Limited-Karachi (Garments Unit)

    Project Duration: 10 months

    Location: Karachi

    Date of Start: March 2016  

    Date of Completion: Dec. 2016

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •     Establishment of IE department for sustainability of the project. 1 IE has hired and trained under the project

    •     OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •     Minimized product travel distance through redesigned layout of stitching production floors and Set up all stitching lines according to product flow

    •     Line balancing through ECRS

    •     Establishment of Lean KPIs

    •     Implemented work station organization

    •     Formulation and Implementation of SoPs and JDs at each level

    •     Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • GIZ – Labour Standard Project: Short term assignment for production layout redesigning in partner Industrial company

    Name of assignment or project: GIZ – Labour Standard Project: Short term assignment for production layout redesigning in partner Industrial company

    Project Duration: 6 months

    Location: Sialkot

    Date of Start: May 2020

    Date of Completion:  November 2020

    Client: CONFIDENTIAL

    Main Project Features: Productivity Improvement through lean manufacturing system

    Positions held: 

    Lean Consultant/Trainer 

    Role in Assignment: 

    Please refer to page # 5

    Activities performed:

    •        Establishment of IE department. 2 IEs have been hired by the company and trained under the project

    •        OJT of workers, line supervisors and middle management on different lean tools and techniques

    •        Set up efficient lean stitching line layout according to product flow

    •        Deployed TPM tools and techniques in Finishing and Packing departments 

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs, like

    (production /day, worker’s efficiency, productivity improvement, Reduction in Quality Defects, Lead Time, WIP, M/c breakdown and 

    reduce manufacturing cost, etc.)

    •        Implemented work station organization 

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • GIZ - Short term consultancy for the Productivity standards component in selected Industrial units (M/s. Vision Technologies (Pvt.) Ltd.,  - Footballs Manufacturer Unit)

    Name of assignment or project: GIZ - Short term consultancy for the Productivity standards component in selected Industrial units (M/s. Vision Technologies (Pvt.) Ltd.,  -

    Footballs Manufacturer Unit)

    Project Duration: 14 months

    Location: Sialkot

    Date of Start: July 2017

    Date of Completion: August 2018

    Client: CONFIDENTIAL

    Main Project Features: To implement labour standards, and to ensure the successful implementation of the dialogue approach for social compliance.  

    Positions held: 

    Lean Consultant/Trainer 

    Role in Assignment: 

    Please refer to page # 9

    Activities performed:

    •        Establishment of IE department for sustainability of the project. 9 IEs have been hired and trained under the project

    •        OJT of workers, Line supervisors and middle & top management on different lean tools and techniques

    •        Minimized product travel distance through redesigned layout of stitching production floors and Set up all stitching lines according to product flow

    •        Line balancing through ECRS

    •        Implemented Preventive Maintenance concepts through TPM tools and techniques 

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 5S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Freelancer, Lean Implementation to improve productivity and quality of their products at M/s. Madrigal Sports Pvt. Ltd., Footballs Manufacturer Unit, Sialkot.

    Name of assignment or project: Freelancer, Lean Implementation to improve productivity and quality of their products at M/s. Madrigal Sports Pvt. Ltd., Footballs Manufacturer Unit, Sialkot.

    Project Duration: 9 months

    Location: Sialkot

    Date of Start: Feb 2020

    Date of Completion: September 2020

    Client: CONFIDENTIAL

    Main Project Features: Productivity Improvement through lean manufacturing system

    Positions held / Role in Assignment: 

    •     Lean Consultant/Trainer 

    •     To conduct baseline study, trainings and implementation of productivity standards improvement measures with monitoring the improvements through key performance indicators (KPIs)

    Activities performed:

    •        Establishment of IE department for sustainability of the project. 1 IEs have been hired and trained under the project

    •        OJT of workers, Line supervisors and middle & top management on different lean tools and techniques

    •        Introduced single piece flow with line balancing through ECRS and Set up efficient lean stitching line 

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Nizam Sons Pvt. Ltd., Sialkot - Gloves Unit

    Name of assignment or project: Productivity Improvement Intervention under European

    Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. Nizam Sons Pvt. Ltd., Sialkot - Gloves Unit

    Project Duration: 11 months

    Location: Sialkot

    Date of Start: March 2016  

    Date of Completion: Jan 2017

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        OJT of workers, Line supervisors and middle & top management on different lean tools and techniques

    •        Minimized product travel distance through re-designed layout of stitching production floors and Set up 4 stitching lines according to product flow

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

     

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Elegant Pvt. Ltd., Murideke (Footwear Unit)

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. Elegant Pvt. Ltd., Murideke (Footwear Unit)

    Project Duration: 9 months

    Location: Murideke

    Date of Start: July 2016  

    Date of Completion: March 2017

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        Introduced new concept of one pair zig-zag line system

    •        Minimized product travel distance 

    •        Line balancing through ECRS

    •        OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

     

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Six A’s Group Pvt. Ltd. Sialkot - Gloves Unit

    Name of assignment or project: Productivity Improvement Intervention under European

    Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. Six A’s Group Pvt. Ltd. Sialkot - Gloves Unit

    Project Duration: 7 months

    Location: Sialkot

    Date of Start: Oct. 2016  

    Date of Completion: April 2017

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •        OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •        Minimized product travel distance through re-designed layout of stitching production floors and Set up an efficient stitching line

    according to product flow

    •        Line balancing through ECRS

    •        Establishment of Lean KPIs

    •        Implemented work station organization

    •        Formulation and Implementation of SoPs and JDs at each level

    •        Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

  • Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness Improvement Program” – PLCIP at M/s. Hafiz Tannery (Pvt.) Ltd.,  – Karachi (Garments Unit)

    Name of assignment or project: Productivity Improvement Intervention under European Union-funded TRTA/PSD III project, titled “Pakistan Leather Competitiveness

    Improvement Program” – PLCIP at M/s. Hafiz Tannery (Pvt.) Ltd.,  – Karachi (Garments

    Unit)

    Project Duration: 11 months

    Location: Karachi

    Date of Start: Jan 2016  

    Date of Completion: Nov. 2016

    Client: CONFIDENTIAL

    Main Project Features: To directly support the GoP trade policy by working along the value chain of the leather products sector in fostering export diversification and the promotion of the leather sector, leading to improved trade competitiveness and enhanced earnings of the country.

    Positions held: 

    Senior Productivity Expert 

    Role in Assignment: 

    Please refer to page # 20

    Activities performed:

    •     Establishment of IE department for sustainability of the project. 1 IE has hired and trained under the project

    •     OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •     Minimized product travel distance through redesigned layout of stitching production floors and Set up all stitching lines according to product flow

    •     Line balancing through ECRS

    •     Establishment of Lean KPIs

    •     Implemented work station organization

    •     Formulation and Implementation of SoPs and JDs at each level

    •     Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

     

  • Small and Medium Enterprises Development Authority” - SMEDA

    Name of assignment or project: During my tenure at “Small and Medium Enterprises Development Authority” - SMEDA, I was engaged as counterpart of different international donor partner experts (JICA. GIZ, BFZ, SES, APO, etc) for the successful implementation of Lean Manufacturing System in the following programs;

    •                 SMEDA-JICA Industry Support Program for Textiles Sector 

    •                 SMEDA Industry Support Program for Auto Sector

    •                 SMEDA-JICA Auto Vendor Development program

    •                 SMEDA Industry Support Program for Fan and Home Appliances

    •                 SMEDA Up-gradation of Foundry Sector

    Project Duration: 10 Years

    Location: Lahore, Sialkot, Karachi, Gujrat, Wazirabad, Gujranwala, etc.

    Date of Start: July 2004            

    Date of Completion: Nov. 2014

    Client: CONFIDENTIAL

    Main Project Features: To provide expertise, knowledge transfer and skill up-gradation for the enhancement of productivity, efficiency and to give know how to local industry for better management practices.

    Positions held: 

    Productivity Advisor

    Role in Assignment: 

    Please refer to page # 22

    Activities performed:

    •     Establishment of IE department for sustainability of the project. 

    •     OJT of workers, Line supervisors and middle management on different lean tools and techniques

    •     Deployed Quality Control Cycles(QCC)

    •     Minimized product travel distance through redesigned layout of production floors and Set up lines according to product flow

    •     Line balancing through ECRS

    •     Establishment of Lean KPIs

    •     Implemented work station organization

    •     Formulation and Implementation of SoPs and JDs at each level

    •     Implemented 6S and visual controls to build organized, safe and efficient production floors

    Impact:  

    On Avg. 15% to 20% Productivity has been achieved and reduced WIP levels, lead times and quality defect as well.     